&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&
1) The cable Rating & Size (Area, Current Rating & Standard Fuse Rating)
2) Transformer Size (capacity KVA).
3) Ring Main Unit (RMU) Types.
4) Feeder Pillar Size (Rating).
By stepping down Voltage Twice from Main-Substation 33KV/11KV ---------> 11KV/415V, we shall see the Meter (*o*). I assume that everyone has seen the Meter since it is spread everywhere (Homes, Malls, Universities ect..). For this reason; I’m going to share with you one of the most common electricity equipment that you may see in your life.
During week #5, the activity that I had been through was; Customer & Services activity. This activity was not really simple and it does not have so much going for site but if they do, they just deliver the electricity bills, customer problem, installing meter & interrupt the electricity supply if it requested earlier from customers. In general; Customer, Services & Metering activity are divided into to three criteria; Metering, Billing & Account and Customer Servicing. During week #5; I was going out with technician for Metering (*o*)
Metering Activity:-
A) Installing Meter.
1. Type of Meter
>> Electronic Meter.
Reads more accurate and gives more details about power consumptions in different unit
>> Mechanical Meter.
Read less accurate than Electronic Meter and gives only one unit of power consumptiom.
2. Type of Customer
>> OPC (Ordinary Power Consumer). Customers which consume a low power electricity .
3. Meter conduct 240V
4. Secure the Meter & Fusion.
>>Cut-Out Fuse (R,Y,B,N) locked by Plastic Secure avoiding electricity interruption from consumer
B) Physical Check.
1. Reading and Recording the Power Consumption KW/h.
2. Type of Customer
>> OPC (Ordinary Power Consumer). Consumers whom has a low cability of consuming electrical power
3. Discuss with customer if complaint occurs.
4. Secure the Meter & Fusion (Mentioned Earlier) .
After all, It was not truly a complicated job but it spent so much time. As I observed that we needed to visit every assigned building to achieve any of those activities mentioned above earlier. Even though this work is not really a hard job nevertheless; it require someone memorize road and address of buildings & houses in such a way to fulfill a complete work simply.
$$$$$$$$$$$
During Thursday (13/5/2010); it was a busy day for the company. Everyone was in rush and there were a meeting then. I had also assigned to Kedai Tenaga technician and I made an appointment that I should come next Monday & Tuesday (17-18/5/2010) to Kedai Tenaga in Putrajaya in such a way to start one of the remaining activities (^_^). Just wait for me; if I have been staying alive next week, I probably would have exposed about it (*o*). –In Sha Allah-
Week 4 was an office week since I started to check out what I had been doing during the past four weeks. As a matter of fact, I begun to prepare and settle my weblog for the past four weeks as well as set my pre-report up even though I had just completed training for around four weeks, nevertheless I believed that it was better to begin before anything get accumulated. In this week, I’d also been getting acquainted more with my new friends (^_^). In other word; I started to get along with my new friends’ trainees since we, all trainees, had been shifted into meeting room and it became our courtyard. Therefore; I started to know them even more. Besides; I consulted about some clarifications about maintenance practice from technicians.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
During Monday (3/5/2010); it was about Safety Presentation Talk to refresh and remind all staffs the essential of safety work and more importantly; the event was also concentrating about the great complete successfully Achievement Google Building in Cyberjaya. Since Google Building was supplied electricity 33KV with a complete and great protection system (/^o^\). The construction work, in general, had been done mostly during April 2010 and the supplement was begun on Sunday (2/5/2010).
During Wednesday (5/5/2010); it was also another gathering ordered by the General Manager (GM). The meeting was totally different from other. It was particularity for the trainee students. This meeting was only for reminding about discipline, policy, rule and regulation of company (TNBD). Furthermore; The GM had assigned the trainee practical a project. There were a 24 titles and the trainee must to select one and they had to get it done before the trainees ended up their training period and they would be giving acknowledgement and certification for complete project.
Furthermore; I’d been gone to Preventive Routine, this work is little bit similar to the maintaining routine for Substation Denominator Home (Main-substation). This time would on the Electrical Substation (Mini-substation).
1. Vacuum Circuit Breaker (VCB).
• Resistance test for the vacuum tank, the mechanism of switch breaker and oil the steel part to avoid Echo
2. Relay Device.
• Cable interconnection, test and troubleshoot.
3. Fault display.
• Test the Overcurrent Protection and Earth fault.
4. Cleaning.
• Wipe SG surface and blowing the dust.
*Here are some general photo about;
During Friday (7/5/2010); it’s a Friday Morning Talk. This ceremony was aiming to reward some staffs and introduced the new incomer trainees and some of new staff. This gather was really impressive since the GM started giving some gifts with certificates acknowledging the work of TNBD staffs. It was truly motivating behavior to encourage not only the other staffs but also the trainees to performance better during work. I wish I could get a opportunity like this before I leave! – In Sha Allah -